Construction of Flyover at Kuril Intersection.
Project Name and Location : Kuril Flyover, Kuril, Airport Road, Dhaka.
Name of the Client / Contract Person : Rajdhani Unnayan Kartripakkha (RAJUK).
Date of Work Order/Starting : 30-03-2010
Description: Construction of Flyover at Kuril Intersection. (Package-FLY-C-01, Lot-01), Memo No- PD/Purbachal/RAJUK/269/2008/297, Date- 30-03-2010. Rajdhani Unnayan Kartripakkha (RAJUK).
Fazilatunnessa Mujib Memorial Specialized Hospital & Nursing College
Project Name and Location : Fazilatunnessa Mujib Hospital & Nursing College, Kashimpur, Gazipur.
Name of the Client / Contract Person : Executative Engineer Gazipur PWD Division, Gazipur.
Date of Work Order/Starting : 13-02-2012
Description: Execution of the works for Sheikh Fazilatunnessa Mujib Memorial Specialized Hospital & Nursing College (1st Phase). Sub-Head: Construction of 2-Storied Guest Dormitory with 4-Storied Foundation & 3 Storied Mosque and Essential Shops with 3-Storied Foundation at Kashimpur, Gazipur.
National Institute of Neurosciences.
Project Name and Location : National Institute of Neurosciences, Sher-e-Bangla Nagar, Dhaka
Name of the Client / Contract Person : "#"
Date of Work Order/Starting : During Year 2011
Description: Raft Fundation, RCC frame structure Building, Brick infill wall and all other finishing work including Civil, Sanitary and Water Supply works, Electrical/ Mechanical works, Gas Connection, Sub station and Generator Room, Generator, Water Pump, Air Conditioning System, PABX, Fire Fighting and Fire Detection System, Glass Cladding works, NEON/POLYSIGN Board, Compound Garden, Gate works, Gas Connection work.
Bangladesh Bank Complex at Barisal
Project Name and Location : Bangladesh Bank Complex, Barisal.
Name of the Client / Contract Person : "#"
Date of Work Order/Starting : During Year 2010
Description: Cast-in-Situ Pile Foundation, RCC Frame Structure Building including Car Parking with Civil, Sanitary and Water Supply, Electrical, Fire Fighting, Supply Installation, Testing and Commissioning of 1830 KVA Sub- Station, Gas Connection work etc.
National Theatre Construction Project
Project Name and Location : Execution of the works for National Theatre Construction Project (2nd phase)
Name of the Client / Contract Person : "#"
Date of Work Order/Starting : During Year 2008
Description: Construction of 7th floor & 8th floor part and finishing of remaining works of 5th floor & 6th floor including 7th floor & open Theatre, Installation of Water supply and Sanitary System & general Electrification Works. Supply and Installation of Air Conditioning System from 5th to 7th Floor. Supply and Installation of Fire Protection and Detection System from 5th to 7th Floor. Supply and Installation of External Electrification and Security Lighting. Supply and Installation of 800 KVA Diesel Generator. Supply and Installation of 3 Nos. Lift. Supply of Furniture etc.
Building of Chittagong Customs
Project Name and Location : Building of Chittagong Customs Clearing & Forwarding Agent's Associationat 122, Sk. Mujib Road, Agrabad Chittagong.
Name of the Client / Contract Person : "#"
Date of Work Order/Starting : During Year 2008
Description: Cast-in-Situ Pile Foundation, RCC frame structure with basement floor, Brick infill wall and all other finishing work including Plumbing, Sanitary works, Electrical works, Gas Line etc.
14-Storied RCC Frame Structure Building Kurmitola, Dhaka.
Project Name and Location : 14-Storied RCC Frame Structure Building, Kurmitola, Dhaka.
Name of the Client / Contract Person : "#"
Date of Work Order/Starting : During Year 2007
Description: RCC Frame Structure Building with Raft Foundation including internal services, Storm Water, Serface Drain and Sewage and Sewerage Disposal etc.
Fazilatunnessa Mujib Memorial Specialized Hospital & Nursing College
Project Name and Location : Fazilatunnessa Mujib Hospital & Nursing College, Kashimpur, Gazipur.
Name of the Client / Contract Person : Public Works Department Executative Engineer Gazipur PWD Division, Gazipur
Date of Work Order/Starting : 25-01-2011
Description: Sheikh Fazilatunnessa Mujib Specialised Hospital & Nursing College Construction Project (1st–Phase). /Administration Bldg./Hostel Bldg./ Nurses Dormitory Bldg. /Doctors Dormitory Bldg./Emergency Staff Quarter/Officers quarter, Construction & Electrical works, for Lot-B.